ISCO Helps Rural Illinois Community Avoid Water Crisis
Fast Action to Build Three Miles of Temporary Pipeline Revives Reservoir
A crisis loomed before Oakland, Illinois, a small town of 1,000 residents in east central Illinois. The dry summer and fall of 1999 resulted in annual rainfall six inches below normal. The dry spell also left the 26-acre Oakland Lake dangerously low. The lake, which draws from an 11,000-acre watershed to provide the city's drinking water supply, has an average depth of 3 feet-9 inches (45 inches). But in November 1999, the lake was 32 inches below normal pool level. Collaborative problem solving, ingenuity, and partnering with ISCO Industries, LLC, helped the City survive the immediate crisis.
It was a desperate situation, observes Garry Bouvet, ISCO Regional Sales Manager. Assuming no additional rainfall, Oakland had only three to four weeks of water, he says. The City had to take action, and take it quickly. Thanks to a call from the Illinois Department of Natural Resources (IDNR), Bouvet was able to apply ISCO's problem-solving expertise to the problem.
The Course of Events Initially, Dale Hanner, Superintendent of Oaklands Water Department, contacted the Illinois Emergency Management Agency (IEMA) for help. The Governors Office stepped in, and IEMA asked IDNRs Office of Water Resources (OWR), to develop a solution to Oaklands problem. According to Hanner, IDNR-OWR studied various alternatives, including drawing on groundwater supplies, pumping from Embarras River, or pumping from a 46-acre lake in Walnut Point State Park about three miles away.
The team, including Oakland Mayor Jim Parks, decided the best alternative was to pump supply water from the lake in Walnut Point State Park into Oakland Lake, which was dropping day by day. They hoped to fill the reservoir to within one foot of normal elevation.
IDNR-OWR put Terry Burke and the Havana maintenance crew in charge of implementing the solution, including construction of the pipeline. IDNRs Fox Waterway Agency (FWA) near Chicago suggested that we contact ISCO for technical services, recalls Burke. One call to ISCO put us in contact with Garry Bouvet in their St. Louis office.
Based on Terrys flow calculations, we needed to allow 16 days of pumping to fill the reservoir, says Bouvet. To establish a timeline, the team also had to figure in pipe delivery time, site constraints, and construction time for the temporary 15,600-foot pipeline. It looked like building the pipeline was manageable, but time clearly was of the essence, he says.
Bouvet consulted with the team both on-site and on-call to finalize an optimum alignment for the aboveground pipeline. He walked and drove the corridor to identify locations that would facilitate access during construction and observation during pumping, provide the shortest distance between the lakes, and simplify pipeline placement. It was like building a three-mile maze from scratch, observes Bouvet.
The team was up against more than time. The final alignment crossed timber areas in Walnut Point State Park, relied on roadside ditches, and ran along the edges of farm fields, through existing culverts, across residential yards, and along the lakes.
Thats not all: to be most cost-effective, the pipeline would need to be constructed of two types of material. The teams plan took advantage of readily available high-density polyethylene (HDPE) and aluminum pipe. A sister division of IDNR-OWR owned the pipe, which was in storage at the FWA site 200 miles away.
IDNR-OWR had purchased the HDPE pipe for FWA several years earlier for dredging operations, but some of the pipe had never been used. The inventory included 3,800 feet of 10-inch HDPE SDR 17 and 26 pipe and 9,300 feet of 8-inch HDPE SDR 32.5 pipe.
The aluminum pipe, owned by the city of Havana, Illinois, had been used during the Midwests 1995 floods. Havana had 4,600 feet of the 10-inch irrigation pipe in 40-foot lengths. The City of Oakland also rented an additional 3,300 feet of aluminum irrigation pipe.
Faster Than Fast-Track The term 'fast track' doesn't even begin to describe this project, says Bouvet, noting that HDPE fusion of the HDPE sections started up a mere five days after Terry Burke's first phone call to Bouvet.
FWA furnished a McElroy fusion machine, and ISCO delivered a second one, plus various fittings for the 10-inch HDPE section of the three-mile line. Bouvet trained the two-person IDNR field crew on the fusion process the two field technicians had never worked with HDPE pipe before. When the 10-inch HDPE run was completed and joined to the aluminum pipe, ISCO brought in a third McElroy fusion machine to facilitate fusion of the 8-inch HDPE section.
Fusion was completed in nine 16-hour days. Garry visited the job site during that time, remaining on call for troubleshooting the entire time. Taking a proactive view also was critical to the success of this plan. Garry was able to help prepare us for anticipated problems and problem solve with quick fixes when necessary, says Burke. He provided a back-up electrofusion machine, and he made sure we had materials on-site to handle the potential problems we tried to anticipate.
With the entire pipeline in place, Oakland was ready to start pumping. The temporary pipeline transmitted about 18 million gallons of water from Walnut Point State Park at a rate of 1,040 gpm at 40 psi in just 13 days. The plan was a success: the reservoir was within one foot of its normal level and the City of Oakland had a supply of water to meet short-term demand.
The HDPE and aluminum pipe was easy to dismantle when the project was completed. Three chainsaws and four hours later, the crew had cut all the joints in preparation for removal.
From the Governors Office approval to construction, pumping, pipeline demolition, and final cleanup, the project took one month. The effort relied on the labor of five IDNR-OWR employees; two employees from the City of Oakland (Hanner and Assistant Superintendent Randy Duzan); two IDNR state park staff members; and 15 to 30 inmates from an Illinois Department of Corrections work camp, plus their supervisors.
This was a monumental team effort lots of work in a very short time, says Bouvet. Sure, ISCO provided fusion equipment and special fittings, says Bouvet, but I think what Im especially proud is that we added value by assisting people in solving their problems with a combination of hardware and good old know-how. That's really the bottom line for ISCO.
IDNRs Terry Burke agrees with this assessment. Garrys round-the-clock availability during fusion and even after pumping got underway was critical we even pumped on Christmas.
Garry brought more than HDPE fittings and fusion equipment to the project he brought essential expertise that helped us avoid a crisis.
Summary ISCO Industries, L.L.C., a technology leader in the HDPE industry, is a fabricator and manufacturer of HDPE piping products.Offering several stocking locations, its corporate headquarters are in Louisville, Kentucky. ISCO manufactures Snap-Tite® at a plant near its corporate headquarters, as well as its facility in Startex, South Carolina. For more information on ISCO Industries, visit www.isco-pipe.com or call 1-800-345-ISCO.
For more information, call ISCO at (800) 345-ISCO, or locate your regional sales representative.
See Alignment & Hydraulic Design Details for this story
Read about more ISCO projects
|